Every campus this county has a public record for, with its status, who it is on record to, and the document each claim rests on. Compiled Sep 17, 2026.

On record

13

Operating

7

Withdrawn or rejected

0

This is a compilation of public records, not a register. A campus can exist without appearing in a filing we read, and a filing can be out of date. Everything here is traceable: the sources section at the back lists the document behind every claim, with the date it carried.

1. What is on record

13 data center campuses are on record in Morrow County, 7 of them operating.

Status What it means Campuses
Operating Recorded as in service. 7
Proposed Someone has proposed it. Nothing has been approved and nothing is being built. 6

Capacity

Megawatt figures come from two very different places and are never added together. No government record in this county states a capacity. A further 2,634 MW is claimed by commercial directories across 10 of 13, which we repeat with attribution and do not treat as measured.

2. Every campus in Morrow County

Campus Status On record to Where Capacity Sources
Amazon Web Services Operating Likely Amazon (AWS)
One circumstantial signal, not a document chain.
Bombing Range Road not stated 1, 2, 3
Amazon Web Services Operating Likely Amazon (AWS)
One circumstantial signal, not a document chain.
Rippee Road not stated 1, 2, 3
Amazon Web Services Operating Likely Amazon (AWS)
One circumstantial signal, not a document chain.
75242 Gar Swanson Drive not stated 1, 2
Amazon Web Services Operating Likely Amazon (AWS)
One circumstantial signal, not a document chain.
75288 Lewis and Clark Drive not stated 1, 2
Amazon Web Services Operating Likely Amazon (AWS)
One circumstantial signal, not a document chain.
Lewis and Clark Drive not stated 1, 2, 3
Amazon Web Services Operating Likely Amazon (AWS)
One circumstantial signal, not a document chain.
79392 Olson Road Southeast not stated 1, 2, 3
amazon web services data center Operating Likely Amazon (AWS)
One circumstantial signal, not a document chain.
rooftop precision not stated 1, 2, 3
Amazon Data Center Proposed Owner not independently traced
Listed as Amazon (AWS) by DataCentersExposed. We have not verified that against a filing.
Heppner not stated 3
AWS Boardman Airport Building 1 Proposed Owner not resolved street precision not stated 2
AWS Threemile Exascale Campus Proposed Owner not resolved street precision not stated 2
Percheron Data Center Proposed Owner not resolved street precision not stated 2
Percheron DC Proposed Likely Rowan Green Data LLC
One circumstantial signal, not a document chain.
rooftop precision not stated 1
Percheron DC Proposed Likely Rowan Green Data LLC
One circumstantial signal, not a document chain.
rooftop precision not stated 1, 3

A campus shown as county only has a record that names Morrow County but no address or coordinate we can stand behind, so it is deliberately not placed on a map or given a distance. It is still counted.

3. Who sells the power

From the utilities' own EIA-861 filings for 2024. A residential rate is not what a data center pays, and it is here as the one published number that lets you compare one utility to another.

Utility Ownership Customers Residential rate
PacifiCorp Investor Owned 1,837,507 13.07 cents/kWh
Umatilla Electric Coop Assn Cooperative 12,620 9.84 cents/kWh
Bonneville Power Administration Federal not stated not stated

4. How to read this

What an empty row means

A blank is written "not stated" throughout, and it means no record we hold states a value. It does not mean zero. A campus with no capacity shown may well have one; no filing we read published it.

What "on record to" means

A name appears without qualification only where a document chain gets from the site to the company: a permit, a filing, a registration. Where a commercial directory asserts an owner and nothing corroborates it, the row says so. Roughly two thirds of all owner information available for US data centers is of that second kind, and treating it as established is the single most common error in this subject.

What this is not

Not a register, not an official list, not a prediction. Data Centers Near Me is an independent compilation of records that are already public. Coverage is deeper in some states than others, and OR is described on the methodology page.

5. Sources

Every numbered source cited in section 2, in the order it first appears. Dates are the date the document itself carries where it has one, and the date we retrieved it where it does not.

  1. Overpass data_center query, tile conus-w1 bbox 24.0,-125.0,50.0,-115.0 · Jun 1, 2026
    https://overpass.kumi.systems/api/interpreter
  2. Cleanview state pages: facility markers (id, name, coordinates, status, MW, county) · Sep 8, 2026 (retrieved)
    https://cleanview.co/data-centers/
  3. dce tracker export (© DataCentersExposed contributors, datacentersexposed.com, ODbL 1.0. Contains data © OpenStreetMap contributors.) · Tue, 08 Se
    https://datacentersexposed.com/data/facilities.csv

Data Centers Near Me. Compiled Sep 17, 2026 from the records listed above. The live version of this county, with the map and every source document, is at https://datacentersnearme.org/counties/oregon/morrow. Corrections are welcome and are published with the record they change.

Free to read, free to share, no account. If a fact here is wrong, the correction form on the site is the fastest way to get it fixed.