Montour County Amazon Data Center
Washingtonville, Montour County, Pennsylvania
Approximate area
A decision-maker refused it.
Status inferred from dce directory (Tue, 08 Se). No filing states it in as many words.
- Status
- Rejected (inferred)
- Owner
- Owner not independently traced
- Capacity
- not stated
- Location known to
- Approximate area
- County
- Montour County
- State
- Pennsylvania
- Electric utility
- PPL Electric Utilities Corp
- Grid operator
- PJM
Location and nearby
Montour County Amazon Data Center is on record as rejected in Montour County, Pennsylvania. 7 other campuses are on record within 25 miles. The nearest is 10.4 mi away, measured between approximate points.
Nearest of each kind: Under construction 13.0 mi Proposed 10.4 mi
Nearest campuses on record
- 10.4 mi approximate
Proposed · Lycoming County, PA
- 12.7 mi approximate
Rejected · Union County, PA
- 13.0 mi approximate
Under construction · Lycoming County, PA
- 14.2 mi approximate
Proposed · Lycoming County, PA
- 22.7 mi approximate
Proposed · Columbia County, PA
- 24.8 mi approximate
AWS Salem Township campus (Susquehanna nuclear plant)
Proposed · Luzerne County, PA
What is on record
Owner
Owner not independently traced
Listed as Amazon (AWS) by DataCentersExposed. We have not verified that against a filing.
What the signal was
-
dce directory attribution
Talen Energy/Amazon
dce tracker export (© DataCentersExposed contributors, datacentersexposed.com, ODbL 1.0. Contains data © OpenStreetMap contributors.) · Jun 18, 2026
Filed by: Talen Energy
- Capacity
- not stated
- Diesel generators
- No air permit found in the records we collect
- Water
- Not collected. State water withdrawal permits are not in this build.
- Electric utility
- PPL Electric Utilities Corp
- Also recorded as
- Amazon · Talen Energy/Amazon
How the status changed
- Rejected Jun 18, 2026 inferred
DCE status 'blocked'
About this data
Evidence
Directory listing only
One or more public directories list it. We have not matched it to a filing.
Location known to
Approximate area
Approximate. Good enough for a neighbourhood, not for a driveway. The point comes from a directory, which does not say how it was derived.
Independent sources
1
directory. Directories count once between them, because they copy each other.
Spotted something wrong? Tell us and we will fix it.
Where this comes from
One source record back this page. Each row is a document we retrieved and kept, so a claim can be checked against the original.
| Document | Role | Row | Date |
|---|---|---|---|
| dce tracker export (© DataCentersExposed contributors, datacentersexposed.com, ODbL 1.0. Contains data © OpenStreetMap contributors.) US | Primary | slug=montour-county-amazon-data-center | Jun 18, 2026 last changed on the server |
© DataCentersExposed contributors, datacentersexposed.com, ODbL 1.0. Contains data © OpenStreetMap contributors.
Free email alerts
Know first when a data center is recorded in Montour County
Each time we refresh the public records and a new campus appears in Montour County, you get one short email naming it, with the document behind it.