Skip to the content
Data Centers Near Me

New York

Data centers in Niagara County

20 campuses are on record here. 1 more was withdrawn or rejected and is kept for the record.

Operating

11

Permitted

1

Proposed

8

Withdrawn

1

14 of 21 are drawn. 7 are on record for the county and no more precisely, so they have no pin.

Every campus on record

Open the printable report for Niagara County

Data centers in Niagara County
Campus Status Owner Capacity
Blockfusion data center Operating (inferred) likely Blockfusion not stated
Blockfusion Niagra Falls Operating (inferred) not traced not stated
Digihost load Operating not resolved 50 MW
Fluidstack Lake Mariner directory listing, unverified Operating (inferred) not traced not stated
H5 Data Centers Buffalo Campus directory listing, unverified Operating (inferred) not resolved not stated
Hut 8 Alpha (Crypto mining) directory listing, unverified Operating (inferred) not resolved not stated
Lake Mariner Data Center directory listing, unverified Operating (inferred) not traced not stated
Lake Mariner WULF Den directory listing, unverified Operating (inferred) not resolved not stated
North Tonawanda Data Center directory listing, unverified Operating (inferred) not resolved not stated
Somerset Load Operating not resolved 250 MW
US Bitcoin data center Operating (inferred) likely US Bitcoin not stated
North East Data LLC Permitted (inferred) not resolved not stated
Anthropic Lake Mariner directory listing, unverified Proposed (inferred) not resolved not stated
DigiHost North Tonawanda AI Data Center directory listing, unverified Proposed (inferred) not traced not stated
Globe Digital Holdings - 1 Proposed not resolved 200 MW
Lake Mariner CB-1 directory listing, unverified Proposed (inferred) not resolved not stated
Lake Mariner Data II Proposed not resolved 250 MW
Niagara Digital Campus Proposed (inferred) not resolved 140 MW
North East Data LLC Data Center Proposed not resolved 500 MW
Wulf Compute Data Center II Proposed not resolved 250 MW
Verizon - Project Oasis Withdrawn not resolved 75 MW

7 of these are known only to the county, so they have no pin on the map and no distance anywhere on this site.

Capacity

Megawatts are only as good as the source. These two lines are never added together.

On record from a filing
1,715 MW
8 of 21 campuses
As reported by directories
1,378 MW
10 of 21 campuses, unverified