Digital Crossroads - CoreWeave Building (301 Digital Crossroads Dr)
Lake County, Indiana
Approximate area
The applicant withdrew it.
Status inferred from cleanview directory (Sep 8, 2026). No filing states it in as many words.
- Status
- Withdrawn (inferred)
- Owner
- Owner not resolved
- Capacity
- 180 MW directory claim
- Location known to
- Approximate area
- County
- Lake County
- State
- Indiana
- Electric utility
- Not identified
- Grid operator
- MISO
Location and nearby
Digital Crossroads - CoreWeave Building (301 Digital Crossroads Dr) is on record as withdrawn in Lake County, Indiana. A directory lists its capacity at 180 MW; no filing we hold states a figure. 38 other campuses are on record within 25 miles, 1 of them within 5 miles. The nearest is 0.18 mi away, measured between approximate points.
Nearest of each kind: Operating 0.18 mi Under construction 11.2 mi Permitted 13.2 mi Proposed 11.2 mi
Nearest campuses on record
- 0.18 mi approximate
Operating · Lake County, IN
- 11.2 mi approximate
Under construction · Cook County, IL
- 11.2 mi approximate
Scott Greenberg Chicago Data Center
Proposed · Cook County, IL
- 11.5 mi approximate
Cyxtera Communications LLC Ch2/Ch4
Operating · Cook County, IL
- 11.9 mi approximate
Iron Mountain Data & Record Storage
Operating · Cook County, IL
- 12.1 mi approximate
Operating · Cook County, IL
What is on record
Owner
Owner not resolved
- Capacity
- 180 MW as reported by cleanview, not from a filing
- Diesel generators
- No air permit found in the records we collect
- Water
- Not collected. State water withdrawal permits are not in this build.
- Electric utility
- More than one utility serves this county, and no filing we hold names which one
How the status changed
- Withdrawn Sep 8, 2026 inferred
Cleanview status 'Canceled'
Cleanview state pages: facility markers (id, name, coordinates, status, MW, county)
About this data
Evidence
Directory listing only
One or more public directories list it. We have not matched it to a filing.
Location known to
Approximate area
Approximate. Good enough for a neighbourhood, not for a driveway. The point comes from a directory, which does not say how it was derived.
Independent sources
1
directory. Directories count once between them, because they copy each other.
Spotted something wrong? Tell us and we will fix it.
Where this comes from
One source record back this page. Each row is a document we retrieved and kept, so a claim can be checked against the original.
| Document | Role | Row | Date |
|---|---|---|---|
| Cleanview state pages: facility markers (id, name, coordinates, status, MW, county) US | Primary | id=1629 | Sep 8, 2026 retrieved by us |
Cleanview (cleanview.co)
Free email alerts
Know first when a data center is recorded in Lake County
Each time we refresh the public records and a new campus appears in Lake County, you get one short email naming it, with the document behind it.