Project Lincoln
La Grange, Oldham County, Kentucky
Approximate area
The applicant withdrew it.
Status inferred from cleanview directory (Sep 8, 2026). No filing states it in as many words.
- Status
- Withdrawn (inferred)
- Owner
- Owner not independently traced
- Capacity
- not stated
- Location known to
- Approximate area
- County
- Oldham County
- State
- Kentucky
- Electric utility
- Not identified
- Grid operator
- PJM
Location and nearby
Project Lincoln is on record as withdrawn in Oldham County, Kentucky. 13 other campuses are on record within 25 miles, 2 of them within 5 miles. The nearest is 1.9 mi away, measured between approximate points.
Nearest of each kind: Operating 9.7 mi Under construction 13.7 mi Proposed 11.7 mi
Nearest campuses on record
- 1.9 mi approximate
Project Lincoln (Oldham County)
Withdrawn · Oldham County, KY
- 3.5 mi approximate
Project Lincoln: OC Data Center
Withdrawn · Oldham County, KY
- 9.7 mi approximate
Operating · Jefferson County, KY
- 11.7 mi approximate
Meta Jeffersonville (proposed)
Proposed · Clark County, IN
- 12.7 mi approximate
Lg&e Ku System Control & Data Center
Operating · Shelby County, KY
- 13.7 mi approximate
Under construction · Clark County, IN
What is on record
Owner
Owner not independently traced
Listed as WHP by Cleanview, DataCentersExposed. We have not verified that against a filing.
What the signal was
-
dce directory attribution
WHP
dce tracker export (© DataCentersExposed contributors, datacentersexposed.com, ODbL 1.0. Contains data © OpenStreetMap contributors.) · Jun 18, 2026
Filed by: WHP
- Capacity
- not stated
- Building area
- 2,500,000 sq ft
- Diesel generators
- No air permit found in the records we collect
- Water
- Not collected. State water withdrawal permits are not in this build.
- Electric utility
- More than one utility serves this county, and no filing we hold names which one
- Also recorded as
- Project Lincoln: OC Data Center (second version) · WHP
How the status changed
- Proposed Jun 18, 2026 inferred
DCE status 'proposed'
- Withdrawn Sep 8, 2026 inferred
Cleanview status 'Canceled'
Cleanview state pages: facility markers (id, name, coordinates, status, MW, county)
About this data
Evidence
Directory listing only
One or more public directories list it. We have not matched it to a filing.
Location known to
Approximate area
Approximate. Good enough for a neighbourhood, not for a driveway. The point comes from a directory, which does not say how it was derived.
Independent sources
1
directory. Directories count once between them, because they copy each other.
Spotted something wrong? Tell us and we will fix it.
Where this comes from
2 source records back this page. Each row is a document we retrieved and kept, so a claim can be checked against the original.
| Document | Role | Row | Date |
|---|---|---|---|
| Cleanview state pages: facility markers (id, name, coordinates, status, MW, county) US | Primary | id=1640 | Sep 8, 2026 retrieved by us |
| dce tracker export (© DataCentersExposed contributors, datacentersexposed.com, ODbL 1.0. Contains data © OpenStreetMap contributors.) US | Primary | slug=project-lincoln-oc-data-center-second-version | Jun 18, 2026 last changed on the server |
Cleanview (cleanview.co) © DataCentersExposed contributors, datacentersexposed.com, ODbL 1.0. Contains data © OpenStreetMap contributors.
Free email alerts
Know first when a data center is recorded in Oldham County
Each time we refresh the public records and a new campus appears in Oldham County, you get one short email naming it, with the document behind it.