DataOne USA / Nebius Vineland (Microsoft)
Vineland, Cumberland County, New Jersey
Approximate area
A permit or approval is on record. Construction may not have started.
Status inferred from agw source doc (Sep 8, 2026). No filing states it in as many words.
- Status
- Permitted (inferred)
- Owner
- Likely Microsoft
- Capacity
- 300 MW
- Location known to
- Approximate area
- County
- Cumberland County
- State
- New Jersey
- Electric utility
- Not identified
- Grid operator
- PJM
Location and nearby
DataOne USA / Nebius Vineland (Microsoft) is on record as permitted in Cumberland County, New Jersey. A record puts its capacity at 300 MW. 3 other campuses are on record within 25 miles, 1 of them within 5 miles. The nearest is 4.4 mi away, measured between approximate points.
Nearest of each kind: Proposed 4.4 mi
Nearest campuses on record
- 4.4 mi approximate
Nebius / DataOne Vineland Phase 2
Proposed · Cumberland County, NJ
- 6.9 mi approximate
Proposed · Cumberland County, NJ
- 13.3 mi approximate
Hexa Builders data center (Black Horse Pike)
Proposed · Gloucester County, NJ
What is on record
Owner
Likely Microsoft
A tracker names this operator and cites a source we have not read ourselves, so it is not traced to a record.
What the signal was
-
cited document names the operator
microsoft
Filed by: NEP Real Estate of Vineland NJ Urban Renewal LLC
Sources name more than one company here: Microsoft, Nebius. That usually means a building with tenants. No source we hold says which is the landlord, so we do not guess.
- Capacity
- 300 MW from agw
- Diesel generators
- No air permit found in the records we collect
- Water
- Not collected. State water withdrawal permits are not in this build.
- Electric utility
- More than one utility serves this county, and no filing we hold names which one
- Also recorded as
- NEP Real Estate of Vineland NJ Urban Renewal LLC; applicant changed to DataOne USA LLC in July 2025 · Nebius · applicant changed to DataOne USA LLC in July 2025
How the status changed
- Permitted Aug 30, 2026 inferred
AI GridWatch stage/outcome: approved|approved; source press
About this data
Evidence
Primary record
A government filing, a federal permit, an assessor parcel or the operator’s own page.
Location known to
Approximate area
Approximate. Good enough for a neighbourhood, not for a driveway.
Independent sources
1
cited filing. Directories count once between them, because they copy each other.
Spotted something wrong? Tell us and we will fix it.
Where this comes from
2 source records back this page. Each row is a document we retrieved and kept, so a claim can be checked against the original.
| Document | Role | Row | Date |
|---|---|---|---|
| Source cited by AI GridWatch for DataOne USA / Nebius Vineland (Microsoft): https://whyy.org/articles/vineland-planning-board-approves-data-center-plan/ US-NJ | Context | url=https://whyy.org/articles/vineland-planning-board-approves-data-center-plan/ | Aug 30, 2026 retrieved by us |
| agw_projects tracker export (AI GridWatch (aigridwatch.com), CC BY 4.0.) US | Context | id=microsoft-nebius-new-jersey | Aug 30, 2026 last changed on the server |
AI GridWatch (aigridwatch.com), CC BY 4.0.
Free email alerts
Know first when a data center is recorded in Cumberland County
Each time we refresh the public records and a new campus appears in Cumberland County, you get one short email naming it, with the document behind it.